(Summary description)AttheinvitationofPetroChinaBohaiDrillingLeaderonAugust16,2019,SuiYuehua,generalmanagerofTaierPetroleumTechnologyCo.,Ltd.,ledateamof4technicalexpertsandfieldengineerstothesiteofXianxi2wellinLenghuTown,Xizhou,Qinghai,tocarryoutleakpluggingconstruction.operation. TherelationshipwithBohaiDrillingbeganinOctober2013.ThecompanyconstructedinYubei,Gansu6inGansu,andencounteredaleakylayer.Thedownholesituationwasextremelycomplicated.ThecompanysuccessfullysolvedthepluggingproblemandleftinthemindoftheBohaidrillingleader.deepimpression. TheXianxi2wellcurrentlyunderconstructionislocatedonthenorthwesternedgeoftheQaidamBasinandhasanaltitudeofnearly2800meters.Thenaturalenvironmentandlivingconditionsareverydifficult.Suihasovercometheenvironmentalandphysicalchallenges.Drawupconstructionmeasuresandsupervisetheentireprocessofpluggingworkonsite.Sofar,thepluggingworkhasbeensmoothandtheeffectisremarkable.NormaldrillinghasbeenresumedandhasbeenhighlyrecognizedbytheleadersofBohaiDrillingCompanyandQinghaiOilfield.
The plugging construction of Xianxi 2 well in Qinghai went smoothly with remarkable results
(Summary description)AttheinvitationofPetroChinaBohaiDrillingLeaderonAugust16,2019,SuiYuehua,generalmanagerofTaierPetroleumTechnologyCo.,Ltd.,ledateamof4technicalexpertsandfieldengineerstothesiteofXianxi2wellinLenghuTown,Xizhou,Qinghai,tocarryoutleakpluggingconstruction.operation. TherelationshipwithBohaiDrillingbeganinOctober2013.ThecompanyconstructedinYubei,Gansu6inGansu,andencounteredaleakylayer.Thedownholesituationwasextremelycomplicated.ThecompanysuccessfullysolvedthepluggingproblemandleftinthemindoftheBohaidrillingleader.deepimpression. TheXianxi2wellcurrentlyunderconstructionislocatedonthenorthwesternedgeoftheQaidamBasinandhasanaltitudeofnearly2800meters.Thenaturalenvironmentandlivingconditionsareverydifficult.Suihasovercometheenvironmentalandphysicalchallenges.Drawupconstructionmeasuresandsupervisetheentireprocessofpluggingworkonsite.Sofar,thepluggingworkhasbeensmoothandtheeffectisremarkable.NormaldrillinghasbeenresumedandhasbeenhighlyrecognizedbytheleadersofBohaiDrillingCompanyandQinghaiOilfield.
- Categories:Corporate News
- Author:
- Origin:
- Time of issue:2020-08-29
- Views:0
At the invitation of PetroChina Bohai Drilling Leader on August 16, 2019, Sui Yuehua, general manager of Taier Petroleum Technology Co., Ltd., led a team of 4 technical experts and field engineers to the site of Xianxi 2 well in Lenghu Town, Xizhou, Qinghai, to carry out leak plugging construction. operation.
The relationship with Bohai Drilling began in October 2013. The company constructed in Yubei, Gansu 6 in Gansu, and encountered a leaky layer. The downhole situation was extremely complicated. The company successfully solved the plugging problem and left in the mind of the Bohai drilling leader. deep impression.
The Xianxi 2 well currently under construction is located on the northwestern edge of the Qaidam Basin and has an altitude of nearly 2800 meters. The natural environment and living conditions are very difficult. Sui has overcome the environmental and physical challenges. Draw up construction measures and supervise the entire process of plugging work on site. So far, the plugging work has been smooth and the effect is remarkable. Normal drilling has been resumed and has been highly recognized by the leaders of Bohai Drilling Company and Qinghai Oilfield.
Scan the QR code to read on your phone
CONTACT US
Add:
Scientific Park of China University of Petroleum, Dongying (No. 1210 South 2nd Road)